Building approval for raising a house on the Gold Coast

Restumping at the same height is usually repair work. Raising the house changes the building, and that is a different conversation with the council.

The distinction that matters

Straight restumping, where existing stumps are replaced at the same height and nothing about the building changes, is commonly treated as repair or maintenance of an existing structure. In many cases that does not require building approval.

Raising a house is different. The height changes, the form changes, and usually the space underneath is intended for some new purpose. That is a change to the building, and it generally does require building approval.

Since the answer depends on the specific property and the specific scope, the responsible position is to confirm rather than assume. A private building certifier or the City of Gold Coast will tell you which category your job falls into, and that conversation is far cheaper than finding out afterwards.

Building without a required approval can result in enforcement action, and in the worst case an order to modify or remove the work. It also surfaces at sale, when a buyer's solicitor asks for approvals that do not exist.

Two different approvals

People use "council approval" as one phrase, but there are two distinct things and a project can need one, both, or neither.

Building approval deals with whether the building work complies with the National Construction Code and the relevant standards. Structure, fire, health and amenity. It is assessed by a building certifier, who can be a private certifier or the council.

Development approval deals with planning: whether the use and form of what you are proposing is acceptable under the City Plan for that site. Height, setbacks, character, flooding, vegetation and so on. Whether you need one depends on how the planning scheme categorises your proposal for your zone and overlays.

A house raise on a straightforward site in a standard residential zone may need building approval only. The same raise on a site with a flood overlay or a character provision may need both.

Timber Queenslander lifted on stacked hardwood cribbing towers and hydraulic jacks with steel beams threaded beneath the floor frame
The approval question is settled long before anything comes off the ground

Overlays worth checking on the Gold Coast

The City Plan applies overlays to properties based on their characteristics, and several of them bear directly on raising a house.

  • Flood overlays. Substantial parts of the city are affected. Where a flood overlay applies, there is usually a defined level that habitable floors are expected to sit above, and this can be the reason for raising in the first place. It also constrains what you can do with the space underneath.
  • Building height. Zones carry height controls, and raising a house increases its overall height. On a two storey outcome this can become the binding constraint.
  • Character and heritage provisions. Some areas have provisions relating to the character of existing dwellings, which can affect what alterations are supported.
  • Landslide, bushfire and vegetation. More relevant in the hinterland, around Tamborine, Currumbin Valley and the western fringes.
  • Setbacks and site cover. Building in underneath can change how the site is counted, even though the footprint has not changed.

The council provides an online mapping tool where you can enter a property address and see the zoning and overlays that apply. It is free and it is the right first step before spending money on design.

The sequence that avoids wasted money

  1. Check the property against the planning scheme using the council's mapping tool. Note the zone and every overlay.
  2. Talk to a private building certifier or a town planner about what those overlays mean for your intended scope. This is the cheapest hour you will spend on the project.
  3. Decide what you actually want. Useful storage and access underneath is a different project to legal habitable rooms, which carry minimum ceiling height requirements under the National Construction Code. Establish which one before design starts.
  4. Engage a designer and engineer to produce the documentation the approval will need.
  5. Obtain development approval if required, then building approval.
  6. Engage the licensed contractor, confirm the QBCC licence, and confirm home warranty insurance is taken out before work starts.
  7. Inspections through the build, then the final certificate. Keep every document.

The most common expensive mistake is running steps 4 and 5 in the wrong order, paying for a design that the overlays were never going to support.

Keep the paperwork

Approvals and final certificates are property records, not project admin. They come up when you sell, when you insure, and when the next owner's solicitor asks what was done to the house and under what approval. Unapproved structural work is a genuine problem at sale and it is much harder to resolve retrospectively than to do properly at the time.

Written August 2026

Check the current rules before you rely on this

This page describes building approval and planning requirements in general terms as at August 2026. Planning schemes, overlays and building requirements change, and what applies depends on the specific property.

Approval requirements are set by the City of Gold Coast and administered by council or a private building certifier. Check your property against the planning scheme using the council's online mapping tool at goldcoast.qld.gov.au, and confirm what applies with a certifier or a town planner. Licensing and home warranty questions belong with the Queensland Building and Construction Commission at qbcc.qld.gov.au.

We are not certifiers, town planners, engineers or lawyers. For what applies to your address, speak to the council or a private building certifier.

Questions

Common questions

Do I need approval to restump my house?

Straight replacement of existing stumps at the same height is commonly treated as repair work and often does not require building approval. Since it depends on your property and the exact scope, confirm it with the City of Gold Coast or a private building certifier rather than assuming.

Do I need approval to raise my house?

Generally yes, because raising changes the height and form of the building. Depending on the zone and the overlays that apply to your site, you may need development approval as well as building approval.

What is the difference between building approval and development approval?

Building approval deals with compliance with the National Construction Code and relevant standards, assessed by a building certifier. Development approval deals with planning matters under the City Plan, such as height, setbacks, character and flooding. A project can need one, both or neither.

How do I find out what overlays apply to my property?

Use the City of Gold Coast online mapping tool at goldcoast.qld.gov.au. Enter the address and it will show the zoning and overlays. Do this before commissioning any design work.

Can I use a private certifier instead of the council?

Private building certifiers assess building approvals in Queensland and are commonly used. Development approval, where required, is a council process. A certifier can tell you which approvals your project needs.

What happens if work was done without approval?

It can result in enforcement action requiring work to stop, be modified or be removed, and it commonly surfaces at sale when approvals are requested. Resolving it retrospectively is possible in some cases but is harder and more expensive than doing it properly at the time.

How high can I raise my house?

There is no universal figure. It depends on the height controls for your zone, any overlays, and whether you intend habitable rooms underneath, which carry minimum ceiling height requirements. Establish this with a certifier or planner before design.

Does raising for flood reasons change the approval process?

Where a flood overlay applies there is usually a defined level that habitable floors are expected to sit above, and that shapes both the design and the assessment. It does not remove the need for approval. Confirm what applies to your address with the council.

Next step

Tell us what the house is doing

Describe the symptoms and the suburb and you will get a straight answer about whether it sounds like stumps, and what an inspection would involve.